A Hard Problem About Software Work

Algebra Level 2

Five people can develop one software application in 13 days. If 2 people are suspended after the 4th day, how many total days will it take to complete the software application?

Note: Only enter the number, no units.


The answer is 19.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

4 solutions

Raj Magesh
May 10, 2014

How many man-days of work will it take to develop the software application? 5 × 13 = 65 5 \times 13 = 65 man-days

How many man-days of work will been completed in 4 days with 5 people? 5 × 4 = 20 5 \times 4 = 20 man-days

How many man-days of work are left? 65 20 = 45 65 - 20 = 45 man-days

How many days will it take to do that much work with only 3 people left? 45 ÷ 3 = 15 45 \div 3 = 15 days

How many days will it taken in total? 4 + 15 = 19 4+15 = \boxed{19} days

Aronas Nuresi
May 9, 2014

1 5 × 13 ( 3 d + 2 × 4 ) = 1 \frac{1}{5\times 13}(3d+2 \times 4)=1

d = 19 \therefore d=19

Ramiel To-ong
Jun 20, 2015

using man - days relationship let x = no. of days needed to finish the job after day 4 5x13 = 4(5) + ( 9 + x )3 x = 6 total number of days = 6 + 9 + 4 = 19 days

Unstable Chickoy
Jun 15, 2014

5 × 4 13 + 3 × ( x 4 ) 13 = 5 \frac{5\times4}{13} + \frac{3\times(x - 4)}{13} = 5

x = 19 x = 19