Five people can develop one software application in 13 days. If 2 people are suspended after the 4th day, how many total days will it take to complete the software application?
Note: Only enter the number, no units.
This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try
refreshing the page, (b) enabling javascript if it is disabled on your browser and,
finally, (c)
loading the
non-javascript version of this page
. We're sorry about the hassle.
5 × 1 3 1 ( 3 d + 2 × 4 ) = 1
∴ d = 1 9
using man - days relationship let x = no. of days needed to finish the job after day 4 5x13 = 4(5) + ( 9 + x )3 x = 6 total number of days = 6 + 9 + 4 = 19 days
1 3 5 × 4 + 1 3 3 × ( x − 4 ) = 5
x = 1 9
Problem Loading...
Note Loading...
Set Loading...
How many man-days of work will it take to develop the software application? 5 × 1 3 = 6 5 man-days
How many man-days of work will been completed in 4 days with 5 people? 5 × 4 = 2 0 man-days
How many man-days of work are left? 6 5 − 2 0 = 4 5 man-days
How many days will it take to do that much work with only 3 people left? 4 5 ÷ 3 = 1 5 days
How many days will it taken in total? 4 + 1 5 = 1 9 days