One man started a project on 1st day. One man joins on each day starting from the second day. The project will be completed in exactly 20 days . Instead, if a team of 7 men work regularly the work will be completed exactly in days. What is the value of ?
This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try
refreshing the page, (b) enabling javascript if it is disabled on your browser and,
finally, (c)
loading the
non-javascript version of this page
. We're sorry about the hassle.
1day - 1 man 2 day - 2men 3 rd day - 3 men ' ' '
formula : (n*(n+1)^2)/2 using this formula we get 210 7 D (days)=210 D=210/7 ans : 30 days