A and B can do a piece of work in 12 days ; B and C can do it in 15 days while C and A can finish it in 20 days . In how many days will A,B,C finish it working together ?
This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try
refreshing the page, (b) enabling javascript if it is disabled on your browser and,
finally, (c)
loading the
non-javascript version of this page
. We're sorry about the hassle.
A+B can do 1/12 th of the work in 1 day. B+C can do 1/15 th of the work in 1 day. C+A can do 1/20th of the work in 1 day.
Therefore, (A+B+C) can do the complete work in how many days?
(A+B+B+C+C+A)/2= A+B+C, hence =>(1/12+1/15+1/20)/2= (12/60)/2= 12/120 A+B+C can complete 12/120 in 1 day. To complete the job ( 120/120), it will take them 120/12 days or 10 days.