There are 900 900 men working on a building, and estimatedly, they will finish in 2 2 years ( 730 730 days). After 455 455 days, 250 250 men left to build another building. How many days can the remaining men do the work? The answer should be estimated to the nearest multiple of 10 10 .


The answer is 380.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

2 solutions

Lee Hang Zheng
Sep 7, 2014

With 900 people, work can be done in 730 days, with 900-250=650 people how long does it take to complete 900 people's worth of 730-455=275 days work? Answer is
(900/650)×275≈380 days. Why? The lesser the people, the longer the time it takes, which is why (900/650) ratio is taken instead of (650/900), I hope it helped, good day.

Let x x be the number of days for the remaining workers to finished the job. Then we have

900 ( 455 ) + 650 x = 900 ( 730 ) 900(455)+650x=900(730)

409500 + 650 x = 657000 409500+650x=657000

650 x = 247500 650x=247500

x 380 days \boxed{x\approx 380~\text{days}}