A job, whereas A needs 20 days to finish and B needs 12 days to finish. If A did x x days first, then B finish the rest of the job, the job will take 14 days to finish. What is x x


The answer is 5.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

1 solution

Jeremy Galvagni
Aug 2, 2018

A does 1/20 of the job per day, B does 1/12 of the job per day.

In x days, A does x/20. In (14-x) days, B does (14-x)/12. To do the whole job then

x 20 + 14 x 12 = 1 \frac{x}{20}+\frac{14-x}{12}=1

1 x 30 + 7 6 = 1 \frac{-1x}{30}+\frac{7}{6}=1

x = 5 x=\boxed{5}