An algebra problem by Tammu Triveni

Algebra Level 1

If 45 men can do a piece of work in 12 days in how many days will 36 men do it?


The answer is 15.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

3 solutions

Mohammad Khaza
Feb 12, 2018

45 45 men do the work in = 12 =12 days.

so, 1 1 man does the work in = 45 × 12 =45 \times 12 days.

therefore, 36 men do the work in = 45 × 12 36 =\frac{45 \times 12}{36} days. = 15 =15 days.

Tammu Triveni
Jun 24, 2014

M1D1=M2D2 , 45x12=36x?, 15 days

Natsir Muhammad
Jun 24, 2014

nalarnya kalo 45 orang aja 12 hari berarti semakin sedikit orang tambah lama dong harinyaa jadi, 45 / 36 = n / 12 n= 15 :)

what the hell are you telling

Anuj Shikarkhane - 6 years, 11 months ago