If 45 men can do a piece of work in 12 days in how many days will 36 men do it?
This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try
refreshing the page, (b) enabling javascript if it is disabled on your browser and,
finally, (c)
loading the
non-javascript version of this page
. We're sorry about the hassle.
4 5 men do the work in = 1 2 days.
so, 1 man does the work in = 4 5 × 1 2 days.
therefore, 36 men do the work in = 3 6 4 5 × 1 2 days. = 1 5 days.