150 workers were engaged to finish a piece of work in a certain number of days. four workers dropped the second day, four more worker dropped the third day and so on. It takes 8 more days to finish the work now. find the number of days in which the work was completed.
This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try
refreshing the page, (b) enabling javascript if it is disabled on your browser and,
finally, (c)
loading the
non-javascript version of this page
. We're sorry about the hassle.
case I work done by 150 people in 'x' days is 150x
case II when 4 workers are being dropped each day the 150x amount of work would take 8 more days Therefore,
150x = {(x+8)/2 } [(2 150)+{(x+8-1)(-4)}]
solving for x will give x=17 17+8 = 25