Danger: Construction Site! Keep out!

Algebra Level 2

Engineer Marvin calculated that a certain construction project can be finished in 200 days by 30 workers. The project started with 30 workers. At the end of 90 days, 10 workers were fired. The remaining workers continued the work for 30 days. Then 30 workers were added to finish the job. After completing the project: were they behind schedule, right on schedule or before schedule?

Note: Assume that all workers have the same rate.

behind schedule before schedule right on schedule

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

1 solution

200 d a y s ( 30 w o r k e r s ) = 90 d a y s ( 30 w o r k e r s ) + 30 d a y s ( 20 w o r k e r s ) + x d a y s ( 50 w o r k e r s ) 200~days(30~workers) = 90~days(30~workers)+ 30~days(20~workers) + x~days(50~workers)

x = 54 d a y s x=54~days

The project was completed in 90 + 30 + 54 = 174 d a y s 90+30+54=174~days . Therefore, they were before schedule.