How long will it take for 3 of them to complete a job ?

Algebra Level pending

If X and Y complete a job in 2 hours, X and Z complete the same job in 3 hours, and Y and Z complete the same job in 4 hours, how long will it take for X, Y, and Z work together to complete the same job?

2 hours 4.5 hours 3 hours 1 hour and 50.77 minutes

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

3 solutions

Chew-Seong Cheong
Nov 22, 2020

Let the work of the job be W W . And the rate of doing work, the amount of W W done per hour, by X X , Y Y , and Z Z be x x , y y , and z z respectively. Then we have:

{ 2 x + 2 y = W x + y = W 2 . . . ( 1 ) 3 x + 3 z = W x + z = W 3 . . . ( 2 ) 4 y + 4 z = W y + z = W 4 . . . ( 3 ) \begin{cases} 2 x + 2 y = W & \implies x + y = \dfrac W2 & ...(1) \\ 3x + 3z = W & \implies x + z = \dfrac W3 & ...(2) \\ 4y + 4 z = W & \implies y + z = \dfrac W4 & ...(3) \end{cases}

( 1 ) ( 2 ) : y z = W 2 W 3 = W 6 . . . ( 4 ) ( 3 ) + ( 4 ) : 2 y = W 4 + W 6 = 5 12 W y = 5 24 W ( 1 ) : x = W 2 5 24 W = 7 24 W ( 3 ) : z = W 4 5 24 W = 1 24 W \begin{array} {rll} (1) - (2): & y - z = \dfrac W2 - \dfrac W3 = \dfrac W6 &...(4) \\ (3)+(4): & 2y = \dfrac W4 + \dfrac W6 = \dfrac 5{12}W \\ & \implies y = \dfrac 5{24} W \\ (1): & \implies x = \dfrac W2 - \dfrac 5{24} W = \dfrac 7{24}W \\ (3): & \implies z = \dfrac W4 - \dfrac 5{24} W = \dfrac 1{24}W \end{array}

Then we have

x + y + z = 7 24 W + 5 24 W + 1 24 W = 13 24 W 24 13 ( x + y + z ) = W \begin{aligned} x + y + z & = \frac 7{24}W + \frac 5{24}W + \frac 1{24}W = \frac {13}{24}W \\ \implies \red{\frac {24}{13}}(x+y+z) & = W \end{aligned}

Therefore it will take 24 13 h o u r s 1 hour 50.77 minutes . \dfrac {24}{13}\ \rm hours \approx \boxed{\text{1 hour 50.77 minutes}}.

Srinivasa Gopal
Nov 21, 2020

If it takes x, y and z hours for the three persons to complete the job if they worked alone. We arrive at the following equations based on the details provided.

1/x + 1/y = 1/2 -- (1)

1/y + 1/z = 1/3----(2)

1/x + 1/z = 1/4----(3)

Adding (1), (2) and (3) yields 2(1/x + 1/y + 1/z) = 1/2 + 1/3 + 1/4 = 13/12

Simplifying we get the value of (1/x + 1/y + 1/z) = 13/24 = 1/T where T is the time taken for all three of them to complete a job if they worked together.

Hence T = 24/13 or 1 hour and 50.77 Minutes.

This is always a nice problem. One point on the answer choices, though - without working anything out, it's obvious that X , Y , Z X,Y,Z together will finish more quickly than just X , Y X,Y ; only one answer option is shorter than the the time it takes X , Y X,Y (ie 2 2 hours), so it must be the correct one.

Chris Lewis - 6 months, 3 weeks ago

Log in to reply

Yes, as a multiple choice question this isn't very challenging. I would note, though, that we cannot just assume that Z makes a positive contribution. That he does is a result of the numbers chosen. If X and Y took 2 hours together, X and Z took 3 hours, and Y and Z took 6 hours, then the math would imply that Z was contributing nothing to the effort.
But, yeah. It would be more challenging if at least one other answer choice were less than 2 hours.

Richard Desper - 6 months, 3 weeks ago

Log in to reply

"Hi guys, can I help?" "Ummm...sure thing, Z, maybe just sit this one out?"

Chris Lewis - 6 months, 3 weeks ago
Eric Roberts
Dec 20, 2020

If X and Y can do it in 2 hrs, X,Y, & Z working together must complete the work in less than 2 hrs! Perhaps the writer should adjust some of the multiple choice answers...hint hint

0 pending reports

×

Problem Loading...

Note Loading...

Set Loading...