A construction company will be penalised each day for delay in construction of a bridge. the penalty will be Rs.4000 for the first day and will increase by Rs.1000 for each following day. Based on its budget, the company can afford to pay a max. of Rs. 165000 towards penalty. find the max. no. of days by which the completion of work can be delayed.

20 30 25 15

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

1 solution

Ashley Shamidha
May 4, 2014

a = 4000 d = 1000 S of n = 165000 n/2[2(4000)+(n-1)(1000)] = 165000 which implies n^2 + 7n - 330 = 0 and n =15 or n = -22 since days cannot be negative n = 15