Level pending

If 20 men can complete work in 40 days . Then in how many days should 4 men leave so that work can be completed in 48 days ?


The answer is 8.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

1 solution

Love Moon
Mar 1, 2015

( Work=Men x Time )

Work complete by 20men x 40days = 800

so that 20xa + 16x(48-a)=800

where, a= day by 20 mans.

By solving this, a=4. Therefore the answer is in 8 days.

Please teach me as this is my first solution.

Yes it's correct !!!

Sarthak Gupta - 6 years, 3 months ago