Production Rate

Algebra Level pending

Al can do a piece of work in 14 days, and working together, Al and Bob can do the same amount of work in 10 days. In what time can Bob alone do the work ?

16 35 20 27 28

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

2 solutions

Tom Engelsman
Mar 4, 2021

If x x be Bob's time alone, then we require:

1 x + 1 14 = 1 10 1 x = 14 10 140 = 1 35 x = 35 \frac{1}{x} + \frac{1}{14} = \frac{1}{10} \Rightarrow \frac{1}{x} = \frac{14-10}{140} = \frac{1}{35} \Rightarrow \boxed{x=35} days.

Bob works 10 ÷ \div 4 4 = = 2.5 2.5 times slower than Al, therefore:

14 14 × \times 2.5 2.5 = = 35 \boxed{35} \Longrightarrow Bob's work time (days)