So much work!!!

Algebra Level 2

10 workers can complete a job in 5 days working 3 hours a day. If 25 workers are working for 1 hour a day, then how many days are required to finish the work?


The answer is 6.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

1 solution

Shobhit Mishra
Sep 20, 2014

man* hours day work= man hours day work ; 10 *3 *5 *1 =25 *1 *day 1 ; 150 = 25*day ; Day=150/25 ; Day=6.