10 workers can complete a job in 5 days working 3 hours a day. If 25 workers are working for 1 hour a day, then how many days are required to finish the work?
This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try
refreshing the page, (b) enabling javascript if it is disabled on your browser and,
finally, (c)
loading the
non-javascript version of this page
. We're sorry about the hassle.
man* hours day work= man hours day work ; 10 *3 *5 *1 =25 *1 *day 1 ; 150 = 25*day ; Day=150/25 ; Day=6.