Some men can do a piece of work in 100 days. When 10 men were less then they complete the work in 110 days. How many men were there initially to do the work?


The answer is 110.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

1 solution

Sunil Sharan
Oct 28, 2014

let there are x men

x.100=(x-10).110

10.x=11.x-110

x=110