Amit completes 1/7 part of his job in 6 days.How many days does he take to complete the whole job.
This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try
refreshing the page, (b) enabling javascript if it is disabled on your browser and,
finally, (c)
loading the
non-javascript version of this page
. We're sorry about the hassle.
If 1/7 part of job is complete, then 6/7 part of job is remaining.
If 1/7 part is done in 6 days, so 6/7 part of job will be completed in 36 days by cross multiplying.
Now add 6 to 36.Therefore, the answer will be 42 days.