A can do a work in 30 days while B can do it in 40 days. In how many days A and B working together can do it?


The answer is 17.14.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

1 solution

Amit Bera
Mar 24, 2016

A can do 1/30th of work in a day B can do it in 1/40th of a in a day therefore, together they will take 1 30 \frac{1}{30} + 1 40 \frac{1}{40} = 7 120 \frac{7}{120} th of work in a day. thus; they will take 120 7 \frac{120}{7} or 17.14 days to finish the work together.