Time and Work problem 3 by Dhaval Furia

Algebra Level pending

Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 13 days, then how many men can finish the job in 13 13 days?


The answer is 13.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

1 solution

Let a man does the work in m m days. Since a machine does the work in 13 × 2 = 26 13\times 2=26 days, we have

78 + 8 m = 2 ( 208 + 3 m ) m = 169 78+8m=2(208+3m)\implies m=169 .

So a man does the work in 169 169 days and hence to finish the work in 13 13 days, 169 13 \dfrac{169}{13} or 13 \boxed {13} men are required.