John can lay a railway track between two given stations in 16 days and Peter can do the same job in 12 days. With Thomas's help, they did the job in 4 days only. Then, Thomas alone can do the job in?
This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try
refreshing the page, (b) enabling javascript if it is disabled on your browser and,
finally, (c)
loading the
non-javascript version of this page
. We're sorry about the hassle.
1 6 1 + 1 2 1 + x 1 = 4 1
x = 9 5 3