UKMT Senior Challenge-VIII

Algebra Level 4

Twenty-five workmen have completed a fifth of a project in eight days. Their foreman then decides that the project must be completed in the next 20 days. What is the smallest number of additional workmen required to complete the project on time?

This problem is not original.This problem is part of this set .


The answer is 15.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

2 solutions

Meriem Kouadria
Jul 4, 2015

Work done in 8 days by 25 men: 1/5

20 days/8 days=2.5

Work done by 25 men in 20 days:2.5/5

Total work by 25 men after 28 days:3.5/5

Remaining work:1.5/5

Number of workmen required:(25x1.5)/2.5=15 workmen

Aryan Gaikwad
Mar 11, 2015

Work done by 25 men = 1 5 \frac { 1 }{ 5 }

Therefore work left = 4 5 \frac { 4 }{ 5 }

25 men can complete 1 5 \frac { 1 }{ 5 } project in 8 days

25 men can complete whole project in 8 5 = 40 8\cdot 5=40 days

1 man can complete the whole project in 40\cdot 25=1000 days

1 man can complete remaining project, ie 4 5 \frac { 4 }{ 5 } project in 4 5 1000 = 800 \frac { 4 }{ 5 } \cdot 1000 = 800 days

Let number of men required be x x

Therefore, for the remaining work to be completed in 20 days, men required =

800 20 = 40 \frac { 800 }{ 20 } =40

Additional men required = 40 - 25 = 15

0 pending reports

×

Problem Loading...

Note Loading...

Set Loading...