"A" and "B" working together can do a piece of work in 12 days and "A" alone can complete the same work work in 18 days. how long will "B" alone take to complete the work.
This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try
refreshing the page, (b) enabling javascript if it is disabled on your browser and,
finally, (c)
loading the
non-javascript version of this page
. We're sorry about the hassle.
1/12 - 1/18 = 1/36 . so "B" alone can do the work in 36 days.