Work, Profit & Loss

Calculus Level 2

A does 80% a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work ?

38 40 37.5 37

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

2 solutions

Venture Hi
Sep 17, 2014

First of all, this isn't a calculus question. The way I approach this is to first find out what is A's work(labor) rate, meaning how much can A do ( in %) per day. We are told that A does 80% in 20 days. Hence, it is short of saying A can do 4% of the work (total work = 100%) in 1 day. It also means that A will finish the work (100%) in 25 days. TOGETHER ( A+B), they both can finish the remaining work that would have taken A 5 days to do in 3 days instead. This means that their combined effort results in doing the remaining 5 days work (100%) in 3 days = 60% (which is 3/5). So if they both started working together, the 25 day job for A will now be a 15 day job for A and B (which is 60% of 25). This means that their combined work effort per day of the total is 6.666% per day. Since we know that by himself A work effort per day = 4% we can now calculate B's work effort per day as 6.66-4 = 2.666%. Using this we can then calculate the number of days if B worked by himself to be 100/2.666 = 37.5 days.

William Asai
Jul 17, 2014

So first what we do is use this simple neat formula Rate [(1/A)+(1/B)]=distance With the information we can say (1/A) 20=4/5 Then A=25 So it takes A 25 days to complete this work Now to find rate of B (1/25+1/B)*3=1/5 Thus we get 3/B=(1/5)-(3/25) 3/B=8/100 B=37.5

0 pending reports

×

Problem Loading...

Note Loading...

Set Loading...