A can do 1/5th of a certain work in 2 days and b can do 2/3rd of it in 8 days. In how much time can they together complete the work?


The answer is 5.45.

This section requires Javascript.
You are seeing this because something didn't load right. We suggest you, (a) try refreshing the page, (b) enabling javascript if it is disabled on your browser and, finally, (c) loading the non-javascript version of this page . We're sorry about the hassle.

1 solution

Finn Hulse
Feb 5, 2014

We see that A can do the job in 10 days, and B can do it in 12 days. That means that they do 1/10 plus 1/12 per day, together. Adding the two and finding the reciprocal gets the answer 5.45.